The contract scope includes all 7.2KV switchgear required for 630KM Sabzab-Rey crude oil pipeline HV/MV substations as well as pump stations.
The approximatly 630KM pipeline will transfer crude oil from Sabzab in Khuzestan provience to Tehran refinary in Rey that is why the project call Sabzav-Rey pipeline project.
The project requires approximalty 150 x 7.2KV feeders which feeds project required electrcity which are going to be delivered partially in seven months